Gully Erosion Threatens Houses, Church, Telecom Mast In Calabar Community, Residents Cry For Help

Residents of a community along the Watt Market to New Airport axis in Calabar have raised the alarm over rapidly expanding gully erosion that has claimed houses, cut off roads, and left families living in fear.

Pastor Cobham Bassey, who said he has lived in the area for about 40 years, said what is now a dangerous gully started as a little gutter that was left unattended. “What you are seeing is gully erosion that is brewing up.

It has been a long time when it was only a little gutter and nothing was done about it. Though we tried to manage it, we ourselves locally, we could not, so till the erosion hit it,” Bassey said.

He said flood water from Watt Market passes through the community to New Airport and has continued to widen the gully over the years. “The water comes from all the way from Watt Market and it passes to New Airport and it crosses over here, and it has been like that for some years now.

It has claimed some houses, like what you are seeing. If you go down, you see other houses that it has claimed,” he said. “Now it has cut this off from the other side. The other side, people can no longer come to this part, and it has been a very dangerous place.”

Bassey said the erosion has also cut off a church in the area, forcing members to stop fellowship there because of the volume and speed of the water, while an Airtel telecom mast is also under threat from sliding.

“There is a church there for a long time, but because of the erosion, it has cut them off and they couldn’t go to the church,” he said.

“The telecom mast, because of the sliding and the weight of the sliding getting to this side, they came around. It is Airtel that owns it, and it has been there for a long time, but because of this sliding, they are trying to stop the sliding, but they could not because of the wideness of what is going on.”

He said several agencies, including the World Bank, and Governor Bassey Otu have visited the site, but nothing has been done. “A lot of agencies have been coming here, and even the governor himself, in his six days in his office, he was here.

He talked to us and we were very happy. But since then we have not seen anything happen, and even the World Bank, they have been coming, and other agencies like that, but they have not done anything,” Bassey said.

Bassey warned that if the erosion is abandoned for another two to three years, more houses will be lost, the road will disappear completely and insecurity will worsen. “My fear is, if this place is abandoned for almost two, three years, there are a lot of people that will park here.

If you look at the distance from the erosion to the house, you know that we are at a risk. It means one day it could claim the house, but there is nothing you can do. You don’t have anywhere else to go, then you are still forced to stay there,” he said.

“That is why we are pleading for the government and the agencies that could help, let them do something about this. That is our happiness, and especially our governor with his goodwill, I believe that he will help his people.”

Reacting to the issue during a telephone conversation, Acting Coordinator of Nigeria Erosion and Watershed Management Project (NEWMAP), in Cross River State, Engr. Obeten Otu, stated that most gully erosion in the state occurs due to poor termination of drainage.

He dismissed the allegation that the administration of Governor Bassey Otu, has abandoned residents of the area, describing it as false. “The government has done the needful. The government has done the design and is preparing to commence tackling of the erosion,” NEWMAP Cordinator said.

He explained that gully erosion control cannot be carried out during the rains, adding that the dry season now provides the window for intervention.

“Nobody does gully erosion control during the rains. It is this season that we have entered now, the dry season, that we want to now see how we can intervene. The design is ready. The Governor has given approval and we have done the design,” he said.
Otu disclosed that there are more than 80 gullies in Cross River State, stressing that the Ekeya site in Calabar is one of the smallest.

He averred that Calabar, the Cross River State capital has a lot of undulating terrain that is prone and susceptible to erosion. “The Governor has given approval to 16 designs that have been completed during this rainy season period,” he added.

Otu further appealed for patience, explaining that erosion control is sequential and cannot be rushed, especially during the rains.

“Even when you are building your house, you cannot cast your concrete during the rainy season, not to talk of embarking on erosion control.

“As I am talking, I am in one of the erosion sites, Summit Hills, which has five gully erosion sites, and we are working on it. This thing is sequential. They should be patient,” he said.